You are here

Construction Projects

Consist of approximately miles of router and crack sealing, miles of maintenance chip and seal, miles of farm access, miles grading projects and miles of misc. grad. All work shall be conducted with in-house personnel and equipment with approximate cost subject to current Budget limits.

12.1 miles of Hot Mix Asphalt (HMA) shall be contracted work. The Hot Mix Asphalt projects shall be managed by the county. County forces shall complete all gravel shoulder reconstruction and crack sealing operations for the HMA projects.

List:

A1601-C: Shetland Rd – 58 Hwy - South 450' Full Depth Mill with 2" HMA = $80,000
A1602-C: 22nd Rd – Milo (75 Hwy) Rd to Reaper Rd 1" Mill with 2" HMA = $600,000
A1603-C: Old 50 Hwy – Fauna Rd to Milo (75 Hwy) Rd w/ 1" Mill with Joints 1" HMA (20'width) and 2" HMA (4' width) =$770,000

Total Estimated Cost = $1,450,000

$1,000,000 (General Fund – Asphalt Line Item) and $450,000 (Special Hwy Improvement Fund)

Wind Farm: Old 50 Hwy – Trefoil Rd to Verdure Rd 1" Mill with 2" HMA Wind Farm expense

Lin ft. of Liner pipe of various sizes shall be installed at several locations in the County listed below. The HDPE Liner is a no-dig approach to rehabilitate the existing damaged culverts. The Lining System is the most cost-effective way with an indefinite service life of the culvert. All work shall be conducted with in-house personnel and equipment with approximate cost of the material being $123,646.80.
Click here for a List of locations

26 miles of Farm Access Projects shall be completed by county forces.
Maintenance-Construction Map

61 miles of roadway striping shall be contracted work managed by the county.

Total estimated Cost = $61,000

128.5 shoulder lane miles (various widths) - Roadway Shoulder Spraying Program. All work shall be completed with in-house personnel and equipment with approximate cost of material of $60,000.
Roadway Shoulder Spraying Map


Webpage last updated:  2016-10-19 15:44:34

Contact Information

Wayne Blackbourn P.E. & P.L.S. Department Head, County Engineer

Highway Department
County Engineer's Office
1510 S 6th St
Burlington, KS 66839

Telephone: 620-364-2441 or 800-947-2897

Fax: 620-364-8271

WBlackbourn@coffeycountyks.org

Hours: Mon - Fri, 7 am - 3:30 pm